Category Archives: Bus

Passenger Seat Partition Fabrication

The passenger side partition panel had been cut out of the bus at some point in the bus’s past, presumably to allow the use of a swiveling seat. Although the restoration will not be 100% accurate, (i.e. non-original safari windows added) having a large part of the interior missing would have been too much of a deviation from original. So in what is probably the most ambitious fabrication project within the bus project so far, a new partition is being created. Luckily, the passenger side partition is somewhat simpler than the driver’s side partition since there are no compound curves required. First a section of tube was heated red hot and bent to the correct radius and welded in place, using a piece of angle iron clamped across the top of both partitions to keep the top tubes co-linear. Next the sheet metal was cut and bent to fit into shape. Finally the sheet metal was welded onto the top of the seat pedestal. The partition will have the raised sections added in the next few days to mirror the raised sections on the driver side partition.

       Leave a comment

Safari Window Test Fit

The safari windows and emblem arrived today and work began on test fitting. Safari window hardware allows both of the front windshields to open upwards to let in fresh air. This was a factory option originally, however the option was not originally installed on this bus. A few of the brackets involved had to be welded to the inside window frame area, this had to occur before paint otherwise the paint would be burnt. However the brackets could not be properly positioned until all of the hardware was installed. So I fully installed the hardware, marked the bracket location, and then fully removed all of the hardware again. After this was completed I welded the brackets; the hardware will be re-installed after paint.

    Leave a comment

Battery Tray Repair

The battery tray had a rust hole in roughly the shape of the bottom of a battery. Years of battery leaks caused this area to rust at a faster rate than the rest of the bus. The repair is mostly complete, all that remains is to finish grinding and shape the repair to more closely match the crease lines of the surrounding metal. The repair required working in an extremely confined location hence this is probably one of the ugliest repairs I’ve done lately; it won’t be noticeable after the body work is completed.

       Leave a comment

Planning…

Tonight I came up with a comprehensive list of all items that must be completed to make the bus a completed shell. Once the shell is completed the bus can be put on it’s final wheel/tires to allow safely raising to a height suitable to work on cleaning/painting on the underside. Once the underside is completed the mechanical/electrical reassembly and restoring/installation of small parts will begin.

    Leave a comment

Bumper Repair

Work started on getting the bumpers ready for primer/bodywork. The front bumper only had a few minor bumps that were straightened out; the rear bumper however had a very deep dent and a tear near one of the brackets. The bumper metal is much thicker than anything else on the bus so removing the rear bumper dent required a considerable amount of beating with an 8lb hammer. Despite the crude method the dent mostly disappeared without introducing much warpage. After the bumpers were straightened paint stripping began, these are among the last remaining parts that are rust-covered. Stripping the inside of the bumpers will require media blasting that will be completed this weekend.

       Leave a comment

Cargo doors detailed

Screw holes on both cargo doors were repaired and the floor was joined to the quarter panel repair.

    Leave a comment

Cargo Doors Installed

Both cargo doors are now installed and for the first time in at least a decade the doors fully open and close without catching on the floor. All of the latch holes line up, so if the latch hardware was installed the doors would latch shut. Pinholes were filled on the quarter panel repair, making this area ready for primer/bodywork.

    Leave a comment

Quarter Panel Repair

The forward cargo door was hung in the door opening and many tweaks were made to achieve a consistent panel gap around all three sides. Previously the rusty/warped bottom of the cargo doors caught against the floor, causing the bottom of the doors to bow outwards. Also, the quarter panel patch was fitted, welded, and ground. The quarter panel still needs to be plug welded to the flanges that intersect it from behind; once this is completed the repair will be 100% complete.

       Leave a comment

More Cargo Door Repair

The repair on the forward cargo door was finished and the same repairs were made on the rear cargo door. The latch plate on the cargo area floor repair section had never lined up with the holes in the rocker panel, the holes in the doors, or the holes above the doors. Luckily all the holes lined up except for the latch plate, so the latch plate was moved to match the rest.

       Leave a comment

Cargo Door Repair

The lower exterior of the forward cargo door was patched. This area had many pinholes along the line where the interior frame joined the door skin and water collected. Welding together the good metal on either side of the pinholes was time consuming but still faster & neater than replacing the lower door skin.

       Leave a comment